Participant Information

Project Timeline

August – September 2026: Participant Registration & Selection

  • Eligible customers contacted
  • Customers complete registration on the platform
  • Customers sign participant agreement


October 2026: Capacity Auction Held

  • Participating customers submit bid details


March 2027: Customer Training

  • Enova and GridS2 to host live training sessions


May – October 2027: Program Window and Activations

  • Activation notices issued by Enova
  • Customers deliver capacity
  • Enova issues Settlement Statements to customers
  • Customers issue monthly invoices to Enova
  • Enova releases program payments monthly


November 2027: Program Completion

  • Post pilot feedback

 

Market Rulebook:

Learn about how the program operates and how payments will be calculated in the Market Rulebook.


Click here to Download

If you are a commercial or industrial customer, or an aggregator working with these customers in the Kitchener South area and can reduce facility demand by at least 100 kW during peak periods then you may be eligible to participate.  Program participants will receive financial compensation based on the performance of their eligible behind-the-meter Distributed Energy Resources (DERs) during activation periods. Activation periods will be preceded by advance notification and are meant to address grid constraints during peak periods.